Cleaver Brooks | Lincoln, Nebraska

44,000 SF Addition to Existing Boiler Manufacturing Facility

  • 52’ Clear Height with 40’ Hook Height for Main Crane Bay
  • 25’x95’ Interior Bays
  • 8” Thick Reinforced Concrete Floor Slab
  • Pre-Engineered Metal Building Structure with Wall and Roof Panels
  • Wet Fire Protection System for Paint Booth and Breakroom/Restrooms
  • 65’ Long x 30’ Wide x 30’ High Paint Booth
  • Crane Rails & Power Supply for Two (2) 100 Ton Capacity Overhead Bridge Cranes
  • Compressor Room with Compressors and Dryers
  • Reclaim Equipment Room for Paint Booth Equipment
  • 2,000 amp Electrical Service Addition
  • 30’x30’ and 25’x25’ Overhead Cooling Steel Doors at Each End of Crane Bay
  • New Concrete Entrance Drive and Rail Crossing
  • Hydro Water System Loop with Drops at Columns
  • Compressed Air Loop System with Drops at Columns
  • Gas Loop System (Natural Gas & Oxygen) with Drops at Columns
  • Power Feeds for Welders and Equipment at Columns